In the critical path method (CPM), what does 'total float' represent for an activity?
-
A
The amount of time an activity can be delayed without delaying the project completion date
-
B
The total labor hours budgeted for the activity
-
C
The number of crew members floating between tasks
-
D
The extra materials kept as buffer stock