Florida General Contractor Cheat Sheet 2026
The 30 highest-yield Florida General Contractor facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
125 questions
405 min time limit
70.00% to pass
- Under Florida law, what is the maximum retainage that can be withheld on a public construction contract once the project is 50% complete? → Retainage can be reduced to 5% after 50% completion
- What is required before beginning work on a construction project? → Building permit
- In Florida, when must a contractor conduct a pre-task safety analysis (JSA) for high-hazard operations? → Before beginning any task identified as high-hazard
- What is a punch list used for in construction? → Final task checklist
- Continuing education for Florida contractors must include a portion on which topic? → Workplace safety and workers' compensation
- Which Florida state agency licenses general contractors through the Construction Industry Licensing Board? → Department of Business and Professional Regulation (DBPR)
- What is the primary function of a 'liquidated damages' clause in a Florida construction contract? → To predetermine the daily cost of delays when actual damages are difficult to calculate
- Under OSHA standards, at what fall height in general construction is fall protection generally required? → 6 feet
- In Florida, what type of pipe material is typically prohibited for use as supply water piping in residential construction due to historical failure issues? → Polybutylene (PB)
- Which delivery method places design and construction under a single contract with the owner? → Design-build
- What is the primary purpose of a confined space entry permit on a Florida construction site? → To ensure all hazards are identified and controlled before entry
- A qualifying agent for a Florida contracting business is primarily responsible for what? → Supervising the company's construction operations
- A performance bond primarily guarantees what? → Completion of the contract per its terms
- Under Florida's Construction Lien Law, within how many days must a subcontractor serve a Notice to Owner after first furnishing labor or materials? → 45 days
- Under Florida law, a construction lien claim must generally be recorded within how many days after the last furnishing of labor or materials? → 90 days
- The difference between a 'certified' and a 'registered' contractor in Florida is that a certified contractor can: → Work statewide
- Under Florida's prompt payment laws, how many days after receiving a complete payment application must an owner pay a contractor on a private project? → 20 days
- Under Florida's Construction Lien Law, how many days does a lienor typically have to record a claim of lien after the last furnishing of labor or materials? → 90 days
- What is required before beginning work on a construction project? → Building permit
- What is the main foundation challenge presented by loosely compacted or disturbed sandy fill soils common in Florida? → Loss of bearing capacity and settlement under structural loads
- Which of the following contract types shifts the most financial risk to the contractor in Florida construction? → Lump-sum (fixed price) contract
- Which Florida board licenses general contractors? → Construction Industry Licensing Board (CILB)
- In a lump-sum (fixed-price) contract, who primarily bears the risk of cost overruns? → The contractor
- Which code governs building standards in Florida? → Florida Building Code
- Which insurance protects a contractor against claims of bodily injury or property damage to third parties? → General liability insurance
- If a contractor's labor burden rate is 30% and base wages are $50,000, what is the total labor cost? → $65,000
- Why are Florida building footings NOT required to be placed at a minimum frost-protection depth? → Florida's climate does not produce freezing ground temperatures
- In a lump-sum (fixed-price) contract, who typically bears the risk of cost overruns? → The contractor
- Under the Florida Building Code, what is required when an air handler unit is installed in an attic space to prevent water damage from condensate overflow? → A secondary drain pan with a separate drain line or overflow switch
- Under Florida Statute Chapter 713, what is the deadline for a contractor to serve a Claim of Lien after the last day of furnishing labor or materials? → 90 days
Turn these facts into recall: