What does the Budget at Completion (BAC) represent in Earned Value Management?
Answer: The total planned cost for the entire project
BAC is the total approved budget allocated for the entire project scope.
Which formula is used to calculate the Estimate at Completion (EAC) when future work is expected to proceed at the planned rate?
Answer: EAC = AC + (BAC - EV)
When future performance is expected at the planned rate, EAC = AC + (BAC – EV), meaning remaining work is done at budget.
A project has a CPI of 0.85. What does this indicate about the project's cost performance?
Answer: The project is over budget — getting only $0.85 of value per dollar spent
A CPI below 1.0 means the project is over budget, delivering less value than the money spent.
What is the Variance at Completion (VAC) formula?
Answer: VAC = BAC - EAC
VAC = BAC – EAC shows the projected difference between the original budget and the expected final cost.
On an EVM project, the Cost Variance (CV) is calculated as:
Answer: EV minus AC
CV = EV – AC; a positive CV means the project is under budget, while a negative CV means over budget.
What is the primary purpose of the To-Complete Performance Index (TCPI)?
Answer: To determine the cost efficiency needed to meet a financial target for remaining work
TCPI shows the required cost efficiency ratio on all remaining work to meet the BAC or EAC target.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- web.aacei.org — Eligibility, fees, passing score, retake fee, time limit, score validity, score release, test delivery, retake policy, test dates · verified Nov 2026