EVM Certification Forecasting & Estimates at Completion 1 — Questions and Answers
Question 1: Which EAC formula assumes all remaining work will be completed at the current Cost Performance Index (CPI)?
- EAC = AC + (BAC - EV)
- EAC = BAC / CPI (Correct answer)
- EAC = AC + ETC
- EAC = BAC - VAC
Correct answer: EAC = BAC / CPI
EAC = BAC / CPI assumes the current cost efficiency will persist for all remaining work on the project.
Question 2: In EVM terminology, what does ETC (Estimate to Complete) represent?
- Total money spent on the project to date
- Total remaining budget from the original plan
- Expected cost needed to complete all remaining project work (Correct answer)
- Difference between BAC and planned value
Correct answer: Expected cost needed to complete all remaining project work
ETC is the expected future cost to finish all remaining project work from the current status point forward.
Question 3: What is the formula for Variance at Completion (VAC)?
- VAC = EV - AC
- VAC = BAC - EAC (Correct answer)
- VAC = PV - EV
- VAC = BAC - AC
Correct answer: VAC = BAC - EAC
VAC = BAC - EAC; a negative result means the project is forecasted to finish over budget.
Question 4: A project has BAC = $200,000, EV = $80,000, and AC = $100,000. What is the EAC using the CPI-based formula?
- $180,000
- $220,000
- $250,000 (Correct answer)
- $240,000
Correct answer: $250,000
CPI = EV/AC = 80,000/100,000 = 0.80; EAC = BAC/CPI = 200,000/0.80 = $250,000.
Question 5: Which EAC formula is considered the most optimistic because it assumes future work is completed at the original planned rate?
- EAC = BAC / CPI
- EAC = AC + (BAC - EV) (Correct answer)
- EAC = AC + (BAC - EV) / CPI
- EAC = AC + (BAC - EV) / (CPI x SPI)
Correct answer: EAC = AC + (BAC - EV)
EAC = AC + (BAC - EV) adds actual costs to remaining budget at face value, assuming no further efficiency loss — the most optimistic recovery assumption.
Question 6: What does TCPI > 1.0 indicate about a project's future performance requirement?
- The project is currently ahead of schedule
- The project must perform more efficiently than current CPI to meet the cost target (Correct answer)
- The project has already exceeded its total budget
- Future work requires less effort than originally planned
Correct answer: The project must perform more efficiently than current CPI to meet the cost target
TCPI > 1.0 means the team must achieve higher cost efficiency on remaining work than demonstrated to date to reach the target.
Question 7: What is the standard formula for calculating ETC from a known EAC?
- ETC = BAC - EV
- ETC = EAC - EV
- ETC = EAC - AC (Correct answer)
- ETC = BAC - AC
Correct answer: ETC = EAC - AC
ETC = EAC - AC; subtracting costs already incurred (AC) from the total forecast (EAC) gives the remaining cost to finish.
Which EAC formula assumes all remaining work will be completed at the current Cost Performance Index (CPI)?