During a plan review for a commercial building, the inspector notices that the electrical drawings lack a fault current calculation. What should the inspector require before approving the plans?
-
A
Approve the plans and note the deficiency for field inspection
-
B
Require the engineer to provide available fault current calculations and equipment interrupting ratings
-
C
Accept the plans if the equipment is listed by a nationally recognized testing laboratory
-
D
Request only the load calculations since fault current is determined in the field