What is a 'lessons learned' process, and when should it occur in design-build?
-
A
Lessons learned only happen after project completion
-
B
Lessons learned should be captured continuously throughout the project at major milestones, enabling real-time improvement
-
C
Lessons learned are only relevant for failed projects
-
D
The owner is solely responsible for documentation