What is the most effective way for a design-build team to maintain alignment with the owner's evolving priorities throughout a long-duration project?
-
A
Review the original RFP quarterly and compare against current status
-
B
Schedule regular owner alignment sessions at defined project milestones to validate goals and priorities
-
C
Have the owner's legal counsel review all project documents monthly
-
D
Assign a dedicated owner liaison from the design-build team with no other responsibilities