What is the best approach for a design-build project manager to resolve a persistent conflict between the lead architect and the structural engineer about a design solution?
-
A
Remove one of the conflicting parties from the project
-
B
Facilitate a structured problem-solving session focused on project requirements and owner goals
-
C
Allow the owner to select the preferred design solution
-
D
Defer the decision until construction begins to see which approach works