A design-build team discovers previously unknown underground utilities during excavation. Under a well-drafted contract, this risk is most likely classified as:
-
A
A design-builder assumed risk requiring no adjustment
-
B
An owner-retained subsurface risk eligible for a contract adjustment
-
C
A force majeure event excusing all parties
-
D
A Type II differing site condition automatically covered by insurance