What are the three primary project delivery methods that owners typically evaluate?
-
A
Low bid, negotiated bid, and sole source
-
B
Design-bid-build (DBB), design-build (DB), and construction manager at-risk (CMAR)
-
C
Architecture, engineering, and construction
-
D
Planning, design, and construction