A state DOT is selecting a delivery method for a highway interchange reconstruction that must minimize lane closures and has a very tight schedule. Which method is most likely selected?
-
A
Design-bid-build with a low-bid award
-
B
Design-build with incentive/disincentive clauses
-
C
Multiple prime contracting
-
D
CM at-risk with cost-plus fee