In Progressive Design-Build, at what stage is the Guaranteed Maximum Price (GMP) typically established?
-
A
During the RFQ/RFP phase before selection
-
B
After the design-build team is selected and sufficient design development occurs
-
C
At project completion during final reconciliation
-
D
Before any design work begins, as a fixed lump sum