Which of the following is a key risk to the owner when issuing an RFP with a highly prescriptive design before procurement?
-
A
Design-builders gain competitive pricing advantages over each other
-
B
The owner assumes greater design liability, reducing the design-builder's single-point responsibility
-
C
Proposals become easier to evaluate due to uniform scope
-
D
Design-builders are relieved of all warranty obligations