What is the owner's primary obligation when issuing a Request for Qualifications (RFQ) in a two-step design-build procurement?
-
A
To select the final design-builder based solely on the RFQ responses
-
B
To evaluate firms' relevant experience, past performance, and key personnel to establish a shortlist of qualified teams
-
C
To negotiate final contract pricing during the RFQ phase
-
D
To disclose confidential project budget information to all respondents