What is the recommended approach for managing subcontractor procurement in design-build?
-
A
All subcontractors must be selected before design begins
-
B
Subcontractors should be engaged progressively as design develops, with key trade partners potentially involved early for their technical input
-
C
Only the lowest bidder for each trade should be selected
-
D
Subcontractor selection is the owner's responsibility in design-build