In a design-build contract, a 'differing site condition' claim is most commonly triggered when:
-
A
The owner changes the project scope after NTP
-
B
Subsurface conditions materially differ from those indicated in contract documents
-
C
The design-builder requests a value engineering change
-
D
Weather delays exceed the contract's allowable threshold