Which DBIA principle emphasizes that the design-builder should assume responsibility for all design and construction to eliminate the owner's exposure to gaps in responsibility?
-
A
Value engineering mandate
-
B
Single point of responsibility
-
C
Collaborative open-book accounting
-
D
Phased permit strategy