Under a design-build GMP contract, 'contingency' held within the GMP by the design-builder is intended to cover:
-
A
Owner-directed scope changes
-
B
Design-builder's risks within the defined scope, such as estimating uncertainty
-
C
Differing site conditions
-
D
Force majeure events