Which of the following best describes the 'turnkey' design-build contracting approach?
-
A
The owner manages design and the contractor only builds
-
B
The design-builder delivers a fully complete, operational facility ready for immediate owner use
-
C
The owner finances construction and the design-builder repays through operations revenue
-
D
Design and construction are bid separately but managed by one firm