A design-build project has a Budget at Completion (BAC) of $10 million, an Earned Value (EV) of $3 million, and an Actual Cost (AC) of $3.6 million. What is the Estimate at Completion (EAC) assuming current CPI continues?
-
A
$10.6 million
-
B
$12 million
-
C
$10 million
-
D
$11.2 million