During a design-build project, the owner's representative discovers that the structural engineer (a key design-build team member) has a pre-existing professional relationship with a subcontractor being evaluated for the steel package. The design-builder's project manager is aware but has not disclosed this. Under DBIA best practices, what is the MOST appropriate immediate action?
-
A
Remove the structural engineer from all subcontractor evaluation activities and document the conflict in the project record
-
B
Allow the structural engineer to continue participating since the relationship was pre-existing and not formed during the project
-
C
Require the owner to waive the conflict in writing before any subcontractor evaluations proceed
-
D
Disqualify the steel subcontractor automatically to eliminate any appearance of impropriety