Substantial completion in a design-build project is best defined as the point when:
-
A
All punch list items are corrected and the owner approves final payment
-
B
The project is sufficiently complete so the owner can occupy or use it for its intended purpose
-
C
The design-builder has submitted all as-built drawings and O&M manuals
-
D
The surety company formally releases the performance bond