A newly formed design-build team is about to begin work on a complex public library. To establish a foundation for high performance and collaboration, what is one of the most critical initial activities the integrated team should undertake?
-
A
Immediately begin creating detailed design drawings to accelerate the schedule.
-
B
Draft a partnering charter to define mutual goals, communication protocols, and issue resolution procedures.
-
C
Procure all long-lead materials to mitigate supply chain risks.
-
D
Complete a detailed risk analysis focused solely on the constructor's financial exposure.