According to DBIA's principles of risk allocation, how should the risk of unforeseen subsurface conditions be handled when the owner possesses but does not disclose a preliminary geotechnical report?
-
A
The risk is shared proportionally between the owner and the design-builder.
-
B
The design-builder assumes the entire risk as part of the single-point responsibility.
-
C
The owner retains the risk, as they are in the best position to manage it by providing known information.
-
D
The risk is transferred to the geotechnical engineer who created the report.