Immediately following contract award for a design-build project, what is the primary purpose of the project kick-off meeting?
-
A
To finalize the selection of major subcontractors and suppliers.
-
B
To mobilize construction equipment and personnel to the site.
-
C
To align the entire integrated team on project goals, communication protocols, and team culture.
-
D
To obtain the final notice to proceed from the owner.