In a Progressive Design-Build (PDB) delivery model, when is the final contract price, such as a Guaranteed Maximum Price (GMP), typically finalized?
-
A
In the initial proposal submitted in response to the RFP, based on conceptual documents.
-
B
After the design is significantly advanced through collaboration between the owner and the design-builder.
-
C
Before the selection of the design-builder, as a prerequisite for team qualification.
-
D
Upon reaching 100% construction documents, immediately prior to the start of construction.