What is a 'critical path method' (CPM) schedule used for in design-build project controls?
-
A
Identifying the longest sequence of dependent activities that determines the project completion date
-
B
Listing all activities in alphabetical order for tracking purposes
-
C
Calculating the maximum number of workers needed on any given day
-
D
Ranking subcontractors by their historical schedule performance