A CVS leading a study for a public agency discovers the agency's estimate contains a major arithmetic error that undermines the project's justification. The CVS should:
-
A
Report the error promptly and objectively to the client
-
B
Ignore it because estimating is not the CVS's responsibility
-
C
Quietly correct it without telling anyone
-
D
Use the error as leverage for a larger contract