During the Information Phase, a VE team leader insists on obtaining the project's cost model before the workshop. The primary purpose of a cost model in VE is to:
-
A
Distribute total cost across elements or functions to reveal high-cost areas
-
B
Replace the owner's approved budget
-
C
Set the contractor's bid price
-
D
Document hourly rates of the VE team