In the VM Information Phase, what is the primary purpose of constructing a cost model?
-
A
To determine the salary of each VM team member
-
B
To allocate total project or product cost to individual functions so high-cost areas can be targeted
-
C
To create a Gantt chart for the VM workshop schedule
-
D
To compare the VM study budget against organizational benchmarks