During an AV project, the client requests a significant scope change after the design phase is complete. What is the FIRST step a CTS should take?
-
A
Begin implementing the change immediately to show responsiveness
-
B
Document the requested change and submit a formal change order
-
C
Refuse the change since the design phase is complete
-
D
Contact the manufacturer to check equipment availability