A stakeholder requests a major change after the project has already started execution. The team leader should FIRST:
-
A
Implement the change immediately to satisfy the stakeholder
-
B
Evaluate the change's impact on scope, cost, and schedule
-
C
Reject the change to protect the project baseline
-
D
Escalate the request to the project sponsor without analysis