A team leader is reviewing a project that has a Cost Performance Index (CPI) of 0.85. This means the project is:
-
A
Earning $1.18 for every dollar spent
-
B
Spending $1.18 for every dollar of value earned
-
C
Ahead of schedule by 15%
-
D
Under budget by 15%