A team leader notices that a project milestone will be missed due to an underestimated task. What should be done FIRST?
-
A
Notify the project sponsor immediately
-
B
Assess the impact on the overall project schedule
-
C
Add more team members to the delayed task
-
D
Request a formal scope change