A contract manager for a Texas state agency discovers that a major deliverable from a contractor is three weeks behind schedule, which could jeopardize the project's overall timeline. According to sound contract administration principles, what is the contract manager's most appropriate initial action?
-
A
Initiate formal dispute resolution procedures immediately.
-
B
Document the delay and communicate with the contractor to understand the cause and discuss corrective actions.
-
C
Terminate the contract for cause due to the contractor's failure to perform.
-
D
Authorize overtime payment to the contractor to expedite the deliverable without a formal contract amendment.