A Preliminary Hazard Analysis (PHA) is typically performed at which stage of a project or system's life cycle?
-
A
During decommissioning and facility closure planning
-
B
After an incident has occurred to determine root causes
-
C
In the early conceptual or design phase, before detailed design is completed
-
D
During routine operations as part of the annual safety audit