CSI Construction Documents & Specifications 2 — Questions and Answers
Question 1: Which MasterFormat level provides the most granular breakdown of work results?
- Level 1 - Division
- Level 2 - Section Group
- Level 3 - Section (Correct answer)
- Level 4 - Article
Correct answer: Level 3 - Section
Level 3 Sections in MasterFormat represent individual work results and are the primary unit used in project specifications.
Question 2: In a project manual, which document typically establishes the contractor's authority to proceed with work?
- The Agreement
- Notice to Proceed (Correct answer)
- Supplementary Conditions
- The Bid Form
Correct answer: Notice to Proceed
The Notice to Proceed is the owner's formal authorization directing the contractor to begin construction on a specific date.
Question 3: What is the primary function of SectionFormat's 'Execution' article?
- Describes required submittals
- Lists referenced standards
- Contains field installation procedures (Correct answer)
- Identifies product substitutions
Correct answer: Contains field installation procedures
The Execution article in SectionFormat details the on-site installation methods, workmanship requirements, and field quality control.
Question 4: A specification that lists acceptable manufacturers but allows substitutions with approval is best characterized as:
- Closed proprietary
- Open generic
- Semi-open or base-bid with substitutions (Correct answer)
- Performance-based
Correct answer: Semi-open or base-bid with substitutions
A semi-open or base-bid with substitutions specification names specific products as the basis of design while permitting approved alternatives.
Question 5: When drawings and specifications conflict, which document typically governs according to standard general conditions?
- Drawings always govern
- Specifications always govern
- The more expensive requirement governs
- The contract documents must be read together and the architect decides (Correct answer)
Correct answer: The contract documents must be read together and the architect decides
AIA A201 and similar general conditions require documents to be read as a whole, with the architect making interpretations when conflicts arise.
Question 6: What does the term 'delegated design' mean in the context of construction specifications?
- The architect delegates drawing production to a draftsperson
- The contractor is responsible for engineering design of a portion of the work (Correct answer)
- The owner delegates design authority to the contractor
- A subconsultant prepares the specifications
Correct answer: The contractor is responsible for engineering design of a portion of the work
Delegated design transfers engineering responsibility for specific work (like connections or shop drawings) to the contractor or a specialty subcontractor.
Question 7: Which CSI publication provides guidance on organizing and writing project specifications?
- MasterFormat
- UniFormat
- The Project Resource Manual (PRM) (Correct answer)
- SectionFormat
Correct answer: The Project Resource Manual (PRM)
The Project Resource Manual (PRM) is CSI's comprehensive guide covering specification writing principles, organization, and best practices.
Which MasterFormat level provides the most granular breakdown of work results?