Project Management for IT Flashcards

7 cards from real CRT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Management for IT flashcards as text
  1. A tobacconist chain's IT director wants to identify which software bugs would cause the most customer impact if not fixed first. Which quality tool prioritizes issues by frequency of occurrence?

    Answer: Pareto chart

    A Pareto chart ranks causes by frequency to highlight the vital few causes responsible for the majority of problems (80/20 rule).

  2. A retail tobacconist's IT project is in its planning phase. The project manager decomposes the total project scope into smaller, manageable components. What is this technique called?

    Answer: Work breakdown structure (WBS) creation

    Creating a WBS hierarchically decomposes the total project scope into work packages that can be scheduled, cost-estimated, and monitored.

  3. During a tobacco retail ERP implementation, the project team must complete testing before training can begin. What type of dependency is this?

    Answer: Mandatory dependency

    A mandatory dependency is inherently required by the nature of the work; training cannot meaningfully precede a working, tested system.

  4. A tobacconist IT project sponsor asks for an early warning system to detect project deviations. Which monitoring approach compares actual performance against the performance measurement baseline?

    Answer: Earned Value Management (EVM)

    EVM integrates scope, schedule, and cost baselines to measure project performance and forecast future performance.

  5. An Agile IT project at a tobacco retailer ends its sprint. The team demonstrates completed work to stakeholders to gather feedback. What is this meeting called?

    Answer: Sprint review

    The Sprint Review is held at the end of a sprint for the team to inspect the increment and adapt the product backlog based on stakeholder feedback.

  6. When managing a tobacco retail IT project, the project manager identifies that a critical vendor may go out of business. The team contracts a backup vendor in advance. Which risk response strategy is this?

    Answer: Risk mitigation

    Mitigation reduces the probability or impact of a risk event; securing a backup vendor reduces the impact of the primary vendor failing.

  7. A project manager for a tobacconist chain's IT upgrade uses expert judgment during the Estimate Activity Durations process. What is the main advantage of this technique?

    Answer: It leverages historical knowledge and experience to improve accuracy

    Expert judgment draws on specialized knowledge and past experience to provide more informed duration estimates, though some uncertainty remains.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. tobacconistuniversity.org — Test delivery, eligibility, fees, exam format, passing score, renewal, retake fee, score validity · verified Oct 2026