A project team is planning using Monte Carlo simulation. What is the primary benefit of this technique for schedule management?
-
A
It provides a single deterministic project end date
-
B
It produces a probability distribution of possible completion dates accounting for uncertainty
-
C
It eliminates the need for three-point estimating
-
D
It calculates the critical path without manual analysis