(CPSM) Certified Software Project Manager Practice Test
CPSM - Certified Software Project Manager CPSM Software Design & Architecture
What is the FIRST consideration when designing a solution in Certified Software Project Manager practice?
Select your answer
A
Available budget constraints
B
Understanding requirements, constraints, and stakeholder needs
C
Selecting the preferred technology or method
D
Establishing the project timeline