A project manager finds that the Schedule Performance Index (SPI) is 0.85. What does this indicate?
-
A
The project is 15% under budget
-
B
The project is progressing at 85% of the planned rate
-
C
The project has completed 85% of its scope
-
D
The project will finish 15% early