A software project's risk probability-impact matrix categorizes a risk as 'High Probability / Low Impact.' What is the most appropriate response?
-
A
Escalate immediately to the project sponsor
-
B
Mitigate by reducing probability or accept with a contingency plan
-
C
Transfer the risk through insurance
-
D
Avoid the risk by canceling the related deliverable