A project team uses statistical process control (SPC) to monitor software defect rates. When should corrective action be triggered?
-
A
Whenever any defect is found
-
B
When data points fall outside the control limits
-
C
After three consecutive sprints complete
-
D
When the project budget exceeds 10%