Which of the following is an example of scope creep?
-
A
The client requests a new feature via a formal change request that is approved
-
B
A developer adds a reporting dashboard that was not in the approved scope without notifying the PM
-
C
The PM updates the WBS to reflect an approved change
-
D
The team completes a deliverable ahead of schedule