A project is 60% complete when the client requests a feature that doubles the original scope. The PM should:
-
A
Implement the feature to maintain the client relationship
-
B
Ignore the request since the project is too far along
-
C
Log a change request, assess impact, and present options to the sponsor
-
D
Split the project into two separate projects immediately