A project manager discovers that two sub-teams have each built separate modules that overlap in functionality. Which integration management process failed?
-
A
Direct and Manage Project Work
-
B
Monitor and Control Project Work
-
C
Develop Project Management Plan
-
D
Perform Integrated Change Control