A sponsor is disengaged and not approving critical decisions. The PM should:
-
A
Proceed with decisions without approval to avoid delays
-
B
Escalate to executive leadership if the sponsor fails to respond after formal outreach
-
C
Replace the sponsor with an alternate contact
-
D
Accept the delays as a normal part of the project