A stakeholder requests a significant scope change late in the project. The PM should:
-
A
Implement the change immediately to keep the stakeholder happy
-
B
Refuse the change to protect the schedule
-
C
Log the request and evaluate it through the formal change control process
-
D
Delegate the decision to the development team