What does the Schedule Performance Index (SPI) measure in Earned Value Management?
-
A
The ratio of Earned Value to Planned Value
-
B
The ratio of Actual Cost to Planned Value
-
C
The total cost variance from the baseline
-
D
The number of milestones completed on time