A project manager uses a tornado diagram during quantitative risk analysis. What does the longest bar in the diagram represent?
-
A
The risk with the earliest expected occurrence date
-
B
The risk with the greatest uncertainty impact on the project objective
-
C
The risk requiring the highest mitigation budget
-
D
The risk most likely to be transferred to a third party